The House of Cherry Family

The building progress of our first house in QLD, Australia.

Thursday, November 20, 2008

Fixing stage

We are now locked up and onto fixing stage.

That means we can't get inside the house without the workers/subcontractors actually being there.

Photos of the kitchen is taken from outside the kitchen window hence the glare and blurry effect.


Kithen installation supposed to start from the 26th of Nov
but we're surprised that it's done.


A better photo of kitchen showing where the stove goes.



The empty wall is for (top) microwave, (bottom) wall oven
and space for the fridge.


A shiny double sink.

Labels: ,

Saturday, November 15, 2008

Laundry tub and vanities


The laundry tub in the corner looks so little.


Our vanities


Unfinished vanity of the kids


Floor still wet from leaking roof the other day.

Labels: , ,

Thursday, November 13, 2008

Internal doors

Internal doors in.. but the roof is leaking!! Notified the supervisor, need to repair the roof and replace the ceiling because of water damage.


Making the door frames



Bathroom and walk-in wardrobe doors







Water marks from the ceiling in the lounge area - caused by heavy rain last night. Extra days for repairs...

Labels:

Saturday, November 8, 2008

Plaster boards and cornices


The contractor working on saturday afternoon


master bedroom


view from family room and the children's shower


bathroom and walk-in wardrobe


kitchen


garage


lounge and dining area


front of house and newly installed double garage door

Labels: , ,